indiviual project mgmt
Mike was hired as a project manager to install hardwood floors for the company Awesome Floor and Tile. They will be installing new flooring into a local office building. Mike comes up with the list of work and estimates the time. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) are estimated in a given table. Following are the activities that are required to install the hardwood floor in the offices:
Activity 2 starts immediately after Activity 1.
Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2.
Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed.
The carpet installation project is complete after Activity 7 is completed.
Your assignment is to write a report that addresses the following:
If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities
OT
MT
PT
Activity 1
2
3
4
Activity 2
3
6
9
Activity 3
4
8
12
Activity 4
6
8
10
Activity 5
8
10
12
Activity 6
10
14
18
Activity 7
4
6
8
You must also do the following:
Please submit your assignment in an APA-formatted paper, using the attached template.
Submitting your assignment in APA format means, at a minimum, you will need the following:
Select your paper details and see how much our professional writing services will cost.
Our custom human-written papers from top essay writers are always free from plagiarism.
Your data and payment info stay secured every time you get our help from an essay writer.
Your money is safe with us. If your plans change, you can get it sent back to your card.
We offer more than just hand-crafted papers customized for you. Here are more of our greatest perks.
Get instant answers to the questions that students ask most often.
See full FAQ