Question 1 of 20 project b

Question 1 of 20 project b

Allocating specific, limited resources to specific activities is called:
A. resource allocation.

B. resource leveling.

C. resource tracking.

D. expediting a project.

Question 2 of 20 5.0 Points

The primary cause of concern in resource allocation is:
A. labor cost.

B. resource scarcity.

C. lack of solution methodologies.

D. parallel activities.

Question 3 of 20 5.0 Points

A project that cannot go over budget is considered:
A. time constrained.

B. schedule constrained.

C. resource constrained.

D. performance constrained.

Question 4 of 20 5.0 Points

The task duration with standard-practice resource usage is referred to as the:
A. expected task duration.

B. nominal task duration.

C. crash duration.

D. normal task duration.

Question 5 of 20 5.0 Points

A task has a normal duration of 9 days and crash duration of 7 days. Its normal cost is $40 and its crash cost is $100. What is the crash cost per day?
A. $140

B. $70

C. $50

D. $30

Question 6 of 20 5.0 Points

What is an expediting technique in which the design and planning phases of a project are not actually completed before the building phase is started?
A. resource loading

B. fast-tacking

C. crashing

D. critical path

Question 7 of 20 5.0 Points

Resource __________ refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.
A. expediting

B. leveling

C. loading

D. allocation

Question 8 of 20 5.0 Points

Which of the following priority rules makes resources available so that activities start on their LSTs whenever possible without increasing the project’s duration?
A. As soon as possible

B. As late as possible

C. Shortest task duration first

D. Minimum slack first

Question 9 of 20 5.0 Points

Which of the following rules maximizes the number of tasks that can be completed by a system in a given period of time?
A. As soon as possible

B. As late as possible

C. Shortest task duration first

D. Minimum slack first

Question 10 of 20 5.0 Points

Several projects can be linked together with:
A. virtual activities.

B. nominal activities.

C. pseudoactivities.

D. ER links.
Reset Selection

Mark for Review What’s This?
Question 11 of 20 5.0 Points

Which of the following is NOT commonly used to help select a priority rule?
A. Schedule slippage

B. Resource utilization

C. In-process inventory

D. Cost overruns
Reset Selection

Mark for Review What’s This?
Question 12 of 20 5.0 Points

Which of the following is a measure of the amount by which a project is delayed by application of a leveling rule?
A. Schedule inflation

B. Schedule progression

C. Schedule efficacy

D. Schedule slippage
Reset Selection

Mark for Review What’s This?
Question 13 of 20 5.0 Points

According to research, the best overall priority rule is:
A. as soon as possible.

B. as late as possible.

C. shortest task duration first.

D. minimum slack first.
Reset Selection

Mark for Review What’s This?
Question 14 of 20 5.0 Points

The practice of assigning project team members to multiple projects is called:
A. concurrent engineering.

B. parallel activities.

C. fast-tracking.

D. multitasking.
Reset Selection

Mark for Review What’s This?
Question 15 of 20 5.0 Points

The safety time added to chains other than the critical chain is called the:
A. feeding buffer.

B. project buffer.

C. path buffer.

D. critical buffer.
Reset Selection

Mark for Review What’s This?
Question 16 of 20 5.0 Points

In traditional Critical Path Method, a second estimate, referred to as the __________ duration, is made based on the resources required to expedite the task.
A. normal task

B. assumed

C. crash

D. approximated
Reset Selection

Mark for Review What’s This?
Question 17 of 20 5.0 Points

When task durations are estimated, an assumption is made that task resources are set at __________ levels.
A. standard

B. normal

C. manageable

D. low
Reset Selection

Mark for Review What’s This?
Question 18 of 20 5.0 Points

Used primarily in the construction industry, the term __________ refers to a technique in which the design and planning phases of a project are not actually completed before the building phase is started.
A. “fast-tracked”

B. “expediting”

C. “crash

Calculate the price of your order

Select your paper details and see how much our professional writing services will cost.

We`ll send you the first draft for approval by at
Price: $36
  • Freebies
  • Format
  • Formatting (MLA, APA, Chicago, custom, etc.)
  • Title page & bibliography
  • 24/7 customer support
  • Amendments to your paper when they are needed
  • Chat with your writer
  • 275 word/double-spaced page
  • 12 point Arial/Times New Roman
  • Double, single, and custom spacing
  • We care about originality

    Our custom human-written papers from top essay writers are always free from plagiarism.

  • We protect your privacy

    Your data and payment info stay secured every time you get our help from an essay writer.

  • You control your money

    Your money is safe with us. If your plans change, you can get it sent back to your card.

How it works

  1. 1
    You give us the details
    Complete a brief order form to tell us what kind of paper you need.
  2. 2
    We find you a top writer
    One of the best experts in your discipline starts working on your essay.
  3. 3
    You get the paper done
    Enjoy writing that meets your demands and high academic standards!

Samples from our advanced writers

Check out some essay pieces from our best essay writers before your place an order. They will help you better understand what our service can do for you.

Get your own paper from top experts

Order now

Perks of our essay writing service

We offer more than just hand-crafted papers customized for you. Here are more of our greatest perks.

  • Swift delivery
    Our writing service can deliver your short and urgent papers in just 4 hours!
  • Professional touch
    We find you a pro writer who knows all the ins and outs of your subject.
  • Easy order placing/tracking
    Create a new order and check on its progress at any time in your dashboard.
  • Help with any kind of paper
    Need a PhD thesis, research project, or a two-page essay? For you, we can do it all.
  • Experts in 80+ subjects
    Our pro writers can help you with anything, from nursing to business studies.
  • Calculations and code
    We also do math, write code, and solve problems in 30+ STEM disciplines.

Frequently asked questions

Get instant answers to the questions that students ask most often.

See full FAQ
    See full FAQ

    Take your studies to the next level with our experienced specialists

    Chat
    Hello, my name is Derreck. Kindly drop your inquiry; I will get back to you shortly. (WhatsApp)+254 729 707 173