Project Management Case 1: Sager Products

Sager Products has been in the business of manufacturing and marketing toys for toddlers for the past two decades. Jim Sager, president of the firm, is considering the development of a new manufacturing line to allow it to produce high-quality plastic toys at reasonable prices. The development process is long and complex. Jim estimates that there are five phases involved and multiple activities for each phase.

Phase 1 of the development process involves the completion of four activities. These activities have no immediate predecessors. Activity A has an optimistic completion time of 2 weeks, a probable completion time of 3 weeks, and a pessimistic completion time of 4 weeks. Activity B has estimated completion times of 5, 6, and 8 weeks; these represent optimistic, probable, and pessimistic time estimates. Similarly, activity C has estimated completion times of 1 week, 1 week, and 2 weeks; and activity D has expected completion times of 8 weeks, 9 weeks, and 11 weeks.

Phase 2 involves six separate activities. Activity E has activity A as an immediate predecessor. Time estimates are 1 week, 1 week, and 4 weeks. Activity F and activity G both have activity B as their immediate predecessor. For activity F, the time estimates are 3 weeks, 3 weeks, and 4 weeks. For activity G, the time estimates are 1 week, 2 weeks, and 2 weeks. The only immediate predecessor for activity H is activity C. Time estimates for activity H are 5 weeks, 5 weeks, and 6 weeks. Activity D must be performed before activity I and activity J can be started. Activity I has estimated completion times of 9 weeks, 10 weeks, and 11 weeks. Activity J has estimated completion times of 1 week, 2 weeks, and 2 weeks.

Phase 3 is the most difficult and complex of the entire development project. It also consists of six separate activities. Activity K has three time estimates of 2 weeks, 2 weeks, and 3 weeks. The immediate predecessor for this activity is activity E. The immediate predecessor for activity L is activity F. The time estimates for activity L are 3 weeks, 4 weeks, and 6 weeks. Activity M has 2 weeks, 2 weeks, and 4 weeks for the estimates of the optimistic, probable and pessimistic time estimates. The immediate predecessor for activity M is activity G. Activities N and O both have activity I as their immediate predecessor. Activity N has 8 weeks, 9 weeks, and 11 weeks for its three time estimates. Activity O has 1 week, 1 week, and 3 weeks as its time estimates. Finally, activity P has time estimates of 4 weeks, 4 weeks, and 8 weeks. Activity J is its only immediate predecessor.

Phase 4 involves five activities. Activity Q requires activity K to be completed before it can be started. The three time estimates for activity Q are 6 weeks, 6 weeks, and 7 weeks. Activity R requires that both activity L and activity M be completed first. The three time estimates for activity R are 1, 2, and 4 weeks. Activity S requires activity N to be completed first. Its time estimates are 6 weeks, 6 weeks, and 7 weeks. Activity T requires that activity O be completed. The time estimates for activity T are 3 weeks, 3 weeks, and 4 weeks. The final activity for phase 4 is activity U. The time estimates for this activity are 1 week, 2 weeks, and 3 weeks. Activity P must be completed before activity U can be started.

Phase 5 is the final phase of the development project. It consists of only two activities. Activity V requires that activity Q and activity R be completed before it can be started. Time estimates for this activity are 9 weeks, 10 weeks, and 11 weeks. Activity W is the final activity of the process. It requires three activities to be completed before it can be started. These are activities S, T, and U. The estimated completion times for activity W are 2 weeks, 4 weeks, and 5 weeks.

Instructions for PM Case 1: Sager Products 

  1. Develop a table showing the activities of the project, the duration of each activity, the ES, EF, LS, LF and slack times.
  2. Determine the expected completion time for the entire process.  Show the variance for each activity and compute for the total project variance.
  3. Determine the critical path and identify the activities on the critical path.
  4. What is the probability that the total project will take less than 40 weeks? 
  5. What is the probability that the total project will take between 35 and 38 weeks?
  6. Write a comprehensive report addressing the problems of the project duration and specifying which activities may require very close management attention. If it appears that the project will not be finished on time, identify the activity or activities which may be considered for crashing, and explain why.

Problem 2 and 3 attached in files  

Calculate the price of your order

Select your paper details and see how much our professional writing services will cost.

We`ll send you the first draft for approval by at
Price: $36
  • Freebies
  • Format
  • Formatting (MLA, APA, Chicago, custom, etc.)
  • Title page & bibliography
  • 24/7 customer support
  • Amendments to your paper when they are needed
  • Chat with your writer
  • 275 word/double-spaced page
  • 12 point Arial/Times New Roman
  • Double, single, and custom spacing
  • We care about originality

    Our custom human-written papers from top essay writers are always free from plagiarism.

  • We protect your privacy

    Your data and payment info stay secured every time you get our help from an essay writer.

  • You control your money

    Your money is safe with us. If your plans change, you can get it sent back to your card.

How it works

  1. 1
    You give us the details
    Complete a brief order form to tell us what kind of paper you need.
  2. 2
    We find you a top writer
    One of the best experts in your discipline starts working on your essay.
  3. 3
    You get the paper done
    Enjoy writing that meets your demands and high academic standards!

Samples from our advanced writers

Check out some essay pieces from our best essay writers before your place an order. They will help you better understand what our service can do for you.

Get your own paper from top experts

Order now

Perks of our essay writing service

We offer more than just hand-crafted papers customized for you. Here are more of our greatest perks.

  • Swift delivery
    Our writing service can deliver your short and urgent papers in just 4 hours!
  • Professional touch
    We find you a pro writer who knows all the ins and outs of your subject.
  • Easy order placing/tracking
    Create a new order and check on its progress at any time in your dashboard.
  • Help with any kind of paper
    Need a PhD thesis, research project, or a two-page essay? For you, we can do it all.
  • Experts in 80+ subjects
    Our pro writers can help you with anything, from nursing to business studies.
  • Calculations and code
    We also do math, write code, and solve problems in 30+ STEM disciplines.

Frequently asked questions

Get instant answers to the questions that students ask most often.

See full FAQ
    See full FAQ

    Take your studies to the next level with our experienced specialists

    Chat
    Hello, we are online 24/7. Leave a message we will reply instantly